Delaware commercial permit fee estimator
New Castle County building permit and State Fire Marshal plan review, for a non-residential renovation or tenant fit-out.
Three jobs, side by side
| Construction cost | Building | Zoning | Occupancy | Fire fund | Fire Marshal | Total |
|---|---|---|---|---|---|---|
| $250,000 | $3,000.00 | $145.00 | $60.00 | $1,250.00 | $1,750.00 | $6,205.00 |
| $1,000,000 | $12,000.00 | $145.00 | $60.00 | $5,000.00 | $7,000.00 | $24,205.00 |
| $3,000,000 | $22,500.00 | $145.00 | $60.00 | $5,000.00 | $13,000.00 | $40,705.00 |
How the numbers are worked out
| Fee | Rule from the document | Row |
|---|---|---|
| County building permit | $12 per $1,000 of valuation up to $1 million and $5.25 per $1,000 over $1 million, $60 minimum. We charge the $5.25 only on the part over $1 million. The sheet does not say so in words, so confirm with the County. | DEC-NCC-01 |
| County zoning permit | 10% of the building permit fee, $21 minimum, $145 maximum. | DEC-NCC-03 |
| County certificate of occupancy | $60. | DEC-NCC-02 |
| County Volunteer Fire Assistance Fund | 0.5% of valuation, on the first $1 million only. | DEC-NCC-04 |
| State Fire Marshal plan review | $150 under $21,428.57. Otherwise 0.7% of cost up to $1 million. Over $1 million: $7,000 plus 0.3% of the amount above $1 million. | DEC-SFM-01 |
Not included in the total
Sewer fees, impact fees (change of use) and a $65 engineering review can apply, and the County sheet gives no amounts for the first two. Trade permits (plumbing, HVAC, refrigeration, hood) are bought after the building permit by a County-licensed contractor, and their fees are not on the sheet we read. Wilmington has its own fees and fire review: not shown. See the fees that may apply.