Delaware Construction Rules

Licenses and process

Each rule below quotes the official document, with its date, the section it came from and the day it was read.

Every New Castle County row applies to a non-residential renovation or tenant fit-out unless the row says otherwise.

County building permit fee

New Castle County charges $12 per $1,000 of valuation up to $1 million and $5.25 per $1,000 over $1 million, with a $60 minimum, for a non-residential renovation or tenant fit-out building permit.

What the document says

$12 per $1,000 of valuation up to $1 Million and $5.25 per $1,000 over $1 Million ($60 Minimum)

Starts: Building permit application.

Watch for: The sheet does not say how partial thousands are handled, so the estimator treats the amount over $1 million as the part charged at $5.25. Confirm with the County.

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Fees, Building Permit Fee. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-01.

County certificate of occupancy fee

The certificate of occupancy fee on this sheet is $60.

What the document says

Certificate of Occupancy: $60

Starts: Certificate of occupancy request.

Watch for: None stated on the sheet.

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Fees, Certificate of Occupancy. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-02.

County zoning permit fee

The zoning permit fee is 10% of the building permit fee, with a $21 minimum and a $145 maximum.

What the document says

10% of Building Permit Fee ($21 Minimum / $145 Maximum)

Starts: Building permit application.

Watch for: None stated on the sheet.

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Fees, Zoning Permit Fee. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-03.

County Volunteer Fire Assistance Fund fee

The New Castle County Volunteer Fire Assistance Fund fee is 0.5% of valuation, charged on the first $1 million of valuation.

What the document says

0.5% of valuation (for the first $1 Million of valuation)

Starts: Building permit application.

Watch for: None stated on the sheet.

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Fees, NCC Volunteer Fire Assistance Fund Fee. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-04.

County fees that may apply

A $65 per review engineering fee may apply to floodplain, wetland or land and grading plan reviews. Sewer fees and impact fees may also apply; the sheet gives no amounts for them.

What the document says

review fee of $65 per review may apply to applicable projects

Applies when: Only on projects that need those reviews or a change of use. Starts: Review or change-of-use filing.

Watch for: Sewer and impact amounts are not on the sheet and are not estimated here.

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Fees, Engineering Fee; Sewer Fees; Impact Fees. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-05.

County plan submission: what is and is not reviewed

The County does not require or review mechanical, electrical and plumbing drawings with the building plan submission, and says they should not be uploaded. Signed and sealed building plans by a Delaware registered design professional are required.

What the document says

MEP drawings are not required or reviewed with the building plan submission and should not be uploaded

Applies when: Building plan submission for a non-residential renovation or tenant fit-out. Starts: Building permit application.

Watch for: The sheet separately lists trade permits obtained after permit issuance (see DEC-NCC-08).

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Documents Required by New Castle County. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-06.

County requires Fire Marshal approval of building plans

The County lists Fire Marshal approval of building plans among the documents it requires for a non-residential renovation or tenant fit-out permit.

What the document says

Fire Marshal Approval of Building Plans

Starts: Building permit application.

Watch for: The sheet does not say whether the State review must come before the County permit. Ask the County.

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Documents Required by New Castle County. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-07.

County contractor license and trade permits

Contractors must be licensed as a permit-endorsed contractor with New Castle County. After the building permit is issued, plumbing, HVAC, refrigeration and hood ventilation permits are obtained by a County-licensed plumbing and/or mechanical contractor.

What the document says

Contractors must be licensed as a permit-endorsed contractor with New Castle County
Plumbing, HVAC, Refrigeration, and Hood Ventilation permits obtained by a NCC licensed plumbing and/or mechanical contractor

Starts: Building permit issued.

Watch for: The sheet says these items 'may be required'. It does not list the County's own license fees or bond amounts.

Source: County permit sheet. Document date: REV. 4/13/2026. Section: Comments. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-08.

County code: who needs a contractor license

New Castle County Code chapter 6 requires a contractor license for people engaged in construction activity where a building, mechanical or plumbing permit is required, where no permit is required, and for subcontractors working under a permit holder's permit.

What the document says

A contractor license is required for persons engaged in the following: A. Construction activity where a building, mechanical, or plumbing permit is required by this Chapter

Applies when: Construction activity in New Castle County covered by chapter 6. Starts: Starting construction activity.

Watch for: The definition lists exclusions, among them State of Delaware Master Electricians listed under electrical contractors and heavy utility construction in the DelDOT right of way. Read the definition before relying on an exclusion. This copy is unofficial.

Source: County code, chapter 6. Document date: As amended through 1/1/2026. Section: Chapter 6, definition of Contractor license. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-09.

County code: bond and insurance for a permit endorsement

A business that wants a County permit contractor endorsement must be separately registered, bonded and insured, and must give the County an A-rated surety bond in the amount set by the code's Appendix schedule. The Appendix schedule is not in the chapter text and was not read.

What the document says

Every business entity must be separately registered, bonded, and insured.

Applies when: Business applying for a permit contractor endorsement in New Castle County. Starts: Application for the endorsement.

Watch for: The bond amounts are in the Appendix, which this service has not read.

Source: County code, chapter 6. Document date: As amended through 1/1/2026. Section: Chapter 6, additional requirements for a permit contractor endorsement. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-NCC-10.

State Fire Marshal building plan review fee

The State Fire Marshal's building plan review fee is $150 for projects under $21,428.57; otherwise 0.7% of construction cost up to and including the first million dollars; over a million, $7,000 plus 0.3% of the amount above $1 million.

What the document says

For any project less than $21,428.57, a minimum $150.00 fee is required for plan submittal.
All others multiply the construction costs by $0.007 for projects up to including the first million.
Projects over a million its $7,000 for the first million and the remainder is multiplied by $0.003 added to the $7,000.

Applies when: New building, or tenant fit out, renovation or change of occupancy application. Starts: Plan submittal to the State Fire Marshal.

Watch for: Payment must be a check, money order or cashier's check payable to the State of Delaware. A site plan approval is required before approval of new, addition or shell and core buildings.

Source: State Fire Marshal plan submittals page. Document date: Page shows no date. Section: Building Plan Review Fee (new building, and tenant fit out, renovation, occupancy change applications). Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-SFM-01.

State license for plumbing and HVACR work

Delaware's Board of Plumbing, Heating, Ventilation, Air Conditioning and Refrigeration Examiners must issue a license before anyone does plumbing or HVACR work in Delaware, including people licensed in another state.

What the document says

Delaware Board of Plumbing, Heating, Ventilation, Air Conditioning and Refrigeration (HVACR) Examiners must issue you a license to so any plumbing or HVACR work in Delaware.

Applies when: Plumbing or HVACR work in Delaware. Starts: Before starting the work.

Watch for: The page says reciprocity may exist, but no current list of qualifying states was found. The quoted answer contains a typo in the source ('to so any').

Source: Plumbing and HVACR board FAQ. Document date: Page shows no date. Section: Frequently Asked Questions, first answer. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-DPR-01.

State board that issues the licenses

The state Board of Plumbing, Heating, Ventilation, Air Conditioning and Refrigeration Examiners issues master plumber, master HVACR and master restricted HVACR licenses. Restricted licenses limit practice to a specialty such as air conditioning. The Board's authority is 24 Del. C. chapter 18.

What the document says

The Board issues master plumber, master HVACR and master restricted HVACR licenses. Restricted licenses limit practice to a specialty such as air conditioning.
The Board’s statutory authority is in 24 Del. C., Chapter 18.

Applies when: Plumbing or HVACR work in Delaware. Starts: Before starting the work.

Watch for: The page says the Board only reviews a complete application and that application fees are non-refundable. It lists no fee amounts on this page.

Source: Plumbing and HVACR board overview. Document date: Page shows no date. Section: Board overview page. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-DPR-02.

Which HVACR license covers which work, and when plumbing needs its own

A Master HVACR license covers design, installation, service and repair of heating, air conditioning, refrigeration, ventilation and process cooling or heating systems, including gas piping. A Master HVACR Restricted license covers one specialty only. Work on water supply and waste pipes and fixtures also needs a Master Plumber license.

What the document says

A Master HVACR can design, install, construct, maintain, service, repair, alter, or modify a product or equipment including gas piping in heating and air conditioning, refrigeration, ventilation, or process cooling or heating systems.
A Master HVACR Restricted license allows you to work in one specialty area.
You need a Master Plumber license in addition to a Master HVACR or Master HVACR Restricted license if you design, install, construct, replace, service, repair, alter, or modify the pipes, fixtures, and other apparatus used for bringing the water supply into a building and removing liquid and water-carried wastes from a building.

Applies when: HVACR or plumbing work in Delaware. Starts: Before starting the work.

Watch for: The page lists six restricted specialties: forced air heating, ventilation and gas piping; hydronic heating and gas piping; commercial hood systems; refrigeration; air conditioning; gas piping. A restricted license holder with a universal CFC card may apply to upgrade to Master HVACR.

Source: Master HVACR licensure page. Document date: Page shows no date. Section: Selecting Type of License. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-DPR-03.

Pennsylvania HVACR license holders applying in Delaware

Pennsylvania does not issue HVACR licenses through a state board. A person whose only current license was issued by a Pennsylvania municipality or other local jurisdiction must apply to the Delaware Board by examination.

What the document says

In the state of Pennsylvania, HVACR licenses are not issued by a state board. If the only current license you hold was issued by a Pennsylvania municipality or other jurisdiction, you must apply by examination.

Applies when: Applicant whose only current HVACR license is from a Pennsylvania municipality or other local jurisdiction. Starts: Application to the Delaware Board.

Watch for: Applicants must also send license verification from every jurisdiction where they hold or ever held a license, a CFC card for some license types, and proof of work experience. This row covers only the Pennsylvania point.

Source: Master HVACR licensure page. Document date: Page shows no date. Section: Requirements for All Applicants. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-DPR-04.

State electrical licenses

The state Board of Electrical Examiners issues licenses to apprentices, journeypersons, master electricians, master electricians special, limited electricians and limited electricians special. The Board's authority is 24 Del. C. chapter 14.

What the document says

The Board issues licenses to apprentices, journeypersons, master electricians, master electricians special, limited electricians, and limited electricians special.
The Board’s statutory authority is in 24 Del. C., Chapter 14.

Applies when: Electrical work in Delaware. Starts: Before starting the work.

Watch for: The page says master special and limited special licenses limit practice to certain specialties such as elevators or HVAC. It lists no fee amounts on this page.

Source: Electrical board overview. Document date: Page shows no date. Section: Board overview page. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-ELE-01.

Electrical license when licensed elsewhere or working for an employer

Delaware requires a license from its Board of Electrical Examiners even if you hold an electrical license in another state. Generally you also need one when you do electrical work only for your employer, with exceptions listed in 24 Del. C. section 1419. Reciprocity depends on whether the other jurisdiction's standards are substantially similar to Delaware's.

What the document says

Yes. The Delaware Board of Electrical Examiners must issue you a license to work in Delaware.
Generally, you must have an electrical license even if you are doing electrical work only for your employer.
you must provide proof of practice for at least five years after licensure.

Applies when: Electrical work in Delaware. Starts: Before starting the work, or when applying by reciprocity.

Watch for: The answer on employer work points to 24 Del. C. section 1419 for exceptions, which this service has not read. The reciprocity answer applies when your current license comes from a jurisdiction whose standards are not substantially similar.

Source: Electrical board FAQ. Document date: Page shows no date. Section: Frequently Asked Questions. Read: 21 Nov 2026. Recheck by: 2027-05-21. Row: DEC-ELE-02.